Amazon settles legal battle against AWS managers accused of data center deal kickbacks Comms tower collapses in Danville, Illinois, after farming machinery catches guy wire DCD Studio: Who decides the future of AI compute? with Piotr Tomasik, TensorWave La Caisse snaps up 49.9% stake in Bell Canada’s tower unit DCD Studio: Building data centers in the US with Jan Jenisch, Amrize Oracle will offer Google’s TPU AI chip via OCI AI and the Physician Shortage: The Strong Case for Urgent, Careful Progress Vodafone Ukraine to install solar arrays across 400 base stations Kushagra Vaid appointed CEO of Omniva SoleCrypt ups size of planned data center campus in Bizerte, Tunisia CoreWeave leasing 22.5MW from atNorth data center in Denmark The Next Competitive Advantage in Drug Development Won’t Be a Better Molecule. It’ll Be Better Patient Selection. Sponsored: The extinction of data breaches: Degauss, destroy, recycle Verizon signs $2bn AWS AI infrastructure deal OpenAI applies for federal permit to build portion of Effingham County, Texas, data center on wetlands – report

First building at Project Jupiter data center campus in New Mexico topped out

The initial stage of Project Jupiter, a significant data center campus in New Mexico constructed by Stack and Oracle, has reached its peak. Clayco and Kiewit New Mexico Co. recently declared the completion of the initial part of the Project Jupiter data center complex in Doña Ana County, New Mexico, by setting the final structural beam on the building and finishing its main structural framework.

Oracle and Stack have selected a joint venture between Clayco and Kiewit as the general contractors for the initial 93,000-square-foot (79,432 sqm) section of the data center campus. Construction is set to begin in October 2025. Clayco’s president of construction and compute, Ryan McGuire, expressed pride in reaching this milestone in Project Jupiter’s construction, stating that it aligns with their mission to improve life through sustainable, advanced technology infrastructure that meets America’s increasing needs. “With the increasing demand for sophisticated technological infrastructure, Clayco is dedicated to providing top-notch data center solutions that contribute to vast community investments and the generation of numerous skilled employment opportunities.

Moreover, these solutions incorporate on-site power generation and eco-friendly water technologies to reduce the strain on local power grids and water networks.” As revealed previously, the campus covers an area of 1,400 acres and will feature four data center structures, along with micro-grid facilities, natural gas power plants, a battery storage center, and a desalination plant. Upon completion of construction, Oracle will take over the campus and utilize it for hosting OpenAI’s AI infrastructure.

The site may reach a capacity of 2.5GW once fully constructed, but the project has allegedly encountered difficulties in obtaining a natural gas connection. Mike Casey, COO of Stack Infrastructure, stated that achieving this milestone demonstrates the exceptional collaboration and dedication of the teams involved in Project Jupiter.

Since the beginning, our primary goal has been to create essential digital infrastructure, with the aim of providing long-term benefits for Doña Ana County. Project Jupiter showcases the potential for large-scale infrastructure to promote technological advancements, create local employment opportunities, enhance the regional economy, and handle energy and water resources in a sustainable manner.

It is an honor for us to collaborate with Oracle, Clayco, Kiewit, and our regional partners in advancing this significant endeavor.”.

 