Hyperscale Data signs 20MW capacity agreement with neocloud customer at its Michigan data center Northwood announces Prism & Portal satellite ground station antennas, targets 10Gbps+ per site Asad Malik named head of compute finance & strategy at Anthropic, joins from Google Blockware appoints Megan Brooks-Anderson as CEO amid AI and HPC push Comtech to sell most of its satcoms segment to Gilat for $157.5m, and pivot to public safety Virginia Approves First-Ever Data Center Power Tax Soltier cryptomine proposal delayed in Bradford County, Pennsylvania Data Centers Take Training into Their Own Hands Amid Talent Shortages New chip could help tiny robots traverse complex environments The $400 million machine powering the future of chipmaking Argentinian gov’t demands Telecom divests spectrum and customers ahead of $1.25bn Telefónica acquisition Sponsored: From air to liquid: Why the transition zone matters Polaroid ads attack data centers for water use Sunrun, Renew Home, and Tesla to aggregate 16GW of home energy resources across US for data center offtakers Bridging the Divide: How Data Centers Are Addressing Community Concerns

Soltier cryptomine proposal delayed in Bradford County, Pennsylvania

Plans for a cryptocurrency mining facility in Bradford County, Pennsylvania, have faced another delay after local planning officials held up progress on the proposal.. The Bradford County planning commission has been reviewing a land development application from Soltier LLC for a proposed crypto data mine at 133 Sullivan Street in Towanda, Wysox Township.. – Google Maps.

The project would be located on a 2.686-acre parcel that already includes gravel parking, driveways, a main building, an attached carport, electrical equipment, and existing Antbox crypto mining machines.. Under the proposal, Soltier would remove the existing gravel and structures on site before regrading the property.

The company is seeking to install a larger electrical service and 27 new Antboxes for crypto mining.. Local broadcaster WENY reported that the county planning commission halted progress on several projects at its June 16 meeting, including the cryptomine proposal and several solar farm developments..

The June 16 agenda listed Soltier’s application as seeking conditional/preliminary approval, contingent on comments from Keystone Associates Architects, a regional architecture, engineering, and surveying firm.. Earlier county documents show the proposal has been moving through the planning process for several months.

The application was tabled at the December 2025 meeting, while a 90-day extension was requested in February 2026. A second submission was received in March, and a review meeting between the engineer and developer was held later that month.. The proposed power capacity of the mining facility has not been disclosed in publicly available planning documents..

The cryptomine application is one of a number of energy-related land development proposals under review in Bradford County. These include the PAL115 Tarbox Solar Project in Canton Township, a proposed 3MW photovoltaic facility from Pivot Energy that would include more than 6,600 solar panels and connect to the grid along State Route 14..

The delays come amid growing scrutiny of crypto mining and other energy-intensive digital infrastructure projects across the US, particularly in rural areas where developments have faced questions over power use, noise, land use, and grid impact.. The Bradford County planning commission is a nine-member board appointed by the county commissioners.

According to the county, the commission advises on coordinated development and administers the county’s subdivision and land development ordinance across most municipalities.. More in Construction & Site Selection. 30 Jan 2026.