UK gov’t looks to introduce tougher prison sentences and unlimited fines to subsea cable saboteurs Reserve Bank of India launches data center in Bhubaneswar, Odisha Data Centers Bring Boom Times, But Will Gains Last? Thieves repeatedly steal copper and tools from Culpeper data center construction site HPE to send Spaceborne Computer-4 to the Moon O2, Nokia complete AI RAN deployment at O2’s Giga Site in London Paddington Fewer Care Delays, More Cost Savings: Nationwide Diagnostic Image Exchange Is Possible With TEFCA Quandela and Quanova partner for deployment of first quantum computer in Vietnam Daedalus supercomputer inaugurated in Greece AWS plans to expand data center footprint in Montgomery County, Missouri Anthropic files S-1 for IPO, with $417bn in compute commitments Verizon signs $2bn AWS AI infrastructure deal Accelerating AI data center deployment with software-defined medium-voltage switchgear Microsoft introduces new sovereignty tools across public and private cloud Bull awarded €40m to deliver HLRE-5 supercomputer to the German Climate Computing Center

Anthropic-linked $366m data center project filed for in Cedar Creek, Texas

A proposal for a $366 million data center project in Cedar Creek, Texas, has been filed with the Texas Department of Licensing and Regulation.. Dubbed Project Longhorn – Building One, the data center will span some 498,165 sq ft (46,281 sqm) and be located at Earl Callahan Road, near Walter Hoffman Road, in Cedar Creek, Bastrop County..

Land between East Callahan Rd and Walter Hoffman Rd – Google Maps. Construction is aiming to begin on November 30, 2026, and be completed by the end of January 2028.. Representatives for Black Chamber, Pacifico Energy, and Anthropic did not respond to BizJournals’ request for comments on a 2,842-acre gas-fired electric generation facility to support a major data center campus in the Cedar Creek area of Bastrop County, which AI lab Anthropic is reportedly in talks to lease..

At full buildout, the project is expected to offer 710MW of “site-rated redundant power using simple-cycle natural gas turbines” that will support 490MW of IT capacity.. The project is located near EdgeConneX’s major campus in the area, for which four more data center buildings were filed in August 2026.

In total, EdgeConneX’s presence in Bastrop County could total more than a dozen buildings across more than 1,500 acres at full build-out. At least part of the capacity is set to be leased to AI cloud firm CoreWeave.. Bastrop County is located outside of Austin, Texas..

Texas as a whole has seen a massive influx of data center projects in recent years, but has begun to resist the tidal wave. In September, Governor Greg Abbott halted all new data center permits from the state’s environmental agency until it completes a large-scale audit of facilities seeking to connect to the Electric Reliability Council of Texas (ERCOT) grid.

ERCOT aims to complete the audit by December.. Despite this, the new filing in Cedar Creek seems to suggest that the project is moving ahead.. Pacifico Energy is the energy arm of investment firm Pacifico Group.

Based out of San Juan, California, the company has interests in both renewable and fossil fuel-based energy projects. Earlier this year, the company secured a 7.65GW air permit from the Texas Commission on Environmental Quality (TCEQ) for its planned 5GW GW Ranch project in West Texas..

Black Chamber Partners is part of a private equity firm with a focus on data center development, typically in Northern Virginia. The group was founded in 2019 and focuses on developing build-to-suit powered shells for hyperscalers.. More in Construction & Site Selection.