Data Centers Bring Boom Times, But Will Gains Last? Ukraine’s Atesh attacks comms tower in Russia’s Belgorod region Bull awarded €40m to deliver HLRE-5 supercomputer to the German Climate Computing Center Microsoft acquires 37 acres in Licking County, Ohio Tesla appoints new head of energy programs SWI launches AI cloud unit SWI Compute Google ordered to suspend site work at two data centers in Finland following tree clearing controversy Cooler Master announces 2.5MW in-row CDU Fireworks to lease data center capacity in Dallas, Texas Suki Secures $90 Million | Confido Health Expands Agentic Operating Platform O2, Nokia complete AI RAN deployment at O2’s Giga Site in London Paddington Verizon signs $2bn AWS AI infrastructure deal G42 signs MoU for AI infrastructure in Greece UK gov’t looks to introduce tougher prison sentences and unlimited fines to subsea cable saboteurs Microsoft introduces new sovereignty tools across public and private cloud

India’s Odisha gov’t approves $18.62m data center project

The Odisha Cabinet has greenlit a Rs 176.83 crore ($18.62m) government data center project in India.

Dubbed the Odisha State Data Centre (OSDC), the facility will be established on the south campus of Dharanidhar University in Keonjhar, reports Analytics India Mag.

Dharanidhar University in Keonjhar

– Dharanidhar University

The data center will be used as a disaster recovery data center for the primary facility located in Bhubaneswar, ensuring services can continue running in the event of outages or cyberattacks.

Because of this, the data center will have an independent power supply, cooling systems, network connectivity, and computing infrastructure.

Of the Rs 176.83 crore ($18.62m) set aside for the project, $16.22m will be for capital expenditure-related costs, while $2.4m will go to operating expenses over a five-year period. More than $17m has been provided by the Fifth State Finance Commission as a grant, while the rest will come from the Electronics and Information Technology Department’s State Data Centre maintenance budget.

The data center is expected to take around nine months to set up, and Krystal Integrated Services has been contracted to assist with the project.

The primary Odisha data center has been operating in Bhubaneswar since 2011. The state is reportedly planning an upgrade of the site, according to OdishaTV. According to that report, the state data center is currently hosting more than 600 government applications.