New Libyan telecom firm to launch data center in 2027 DCD Studio: AI’s power problem with Varun Sivaram, Emerald AI ZTE unveils data center module designed for AI workloads Kao Data to host CommonAI’s AI Scaling Inference Lab at Harlow data center Meta details Ohio Prometheus data center campus, with first phase live Bonus Features – October 25, 2026 – 40% of orgs say identity authentication difficulties delay patient care, Epic introduces Connectors for third-party apps, plus 34 more stories Core Stack JV adds more data centers to €1bn Italy network Sponsored: GF completes LiquidCore portfolio with intelligent Multi Control Valve to maximize direct liquid cooling efficiency Google ordered to suspend site work at two data centers in Finland following tree clearing controversy Quandela and Quanova partner for deployment of first quantum computer in Vietnam HPE to send Spaceborne Computer-4 to the Moon Sponsored: Belimo strengthens global data center strategy with new Experience Center in the Americas Thieves repeatedly steal copper and tools from Culpeper data center construction site Short seller bets against Csquare, says data center firm’s shares are worthless UK gov’t looks to introduce tougher prison sentences and unlimited fines to subsea cable saboteurs

Pure starts work on second building at Brent Cross campus in London, UK

UK operator Pure Data Centres has started work on the second building at its Brent Cross campus in London.. – Pure Data Centres. Pure Data Centres Group this week announced the start of its final major build phase at its LON01 Brent Cross campus in North London.. General contractor Glencar has commenced piling works for the West Shell of the 70MW LON01 B2 facility..

This second phase of development will extend the campus by more than 23,000 sqm (247,570 sq ft) and bring total capacity to 90MW.. Completion of the wider B2 facility is scheduled for Q2 2029.. LON01 will feature closed-loop liquid cooling to support high-density AI inference and cloud workloads..

B2 will also be home to one of the world’s largest living walls, with more than 750,000 plants.. Glencar’s scope includes delivery of the West Cold Shell, incorporating piling and foundations, underground services and associated works, structural frame and connections to the adjacent East Cold Shell, concrete and slab works, stair cores, building envelope and roofing..

Dan Priest, campus delivery director, Pure DC, said: “Piling commencement represents an important milestone in the continued development of our Brent Cross campus. LON01B2 is a major part of our investment in London’s digital infrastructure, and it is encouraging to see the final stage of construction now progressing on site.

We look forward to continuing to work closely with Glencar and the wider project team as the development moves forward.”. Pure was established in 2015 and is backed by funds managed by Oaktree Capital Management. The London-based company currently has more than 500MW of IT capacity in operation or development in markets across Europe, Asia, and the Middle East.

The company has projects live and in development across London, Paris, Amsterdam, Dublin, Abu Dhabi, Madrid, Jakarta, and Seinäjoki.. Roy Jones, managing director of London and the South at Glencar, added: “Seeing piling get underway marks the transition into the structural phase of the programme.

Delivering a project of this scale within a live and highly constrained data centre campus requires detailed planning, close collaboration and careful coordination across every stage.”. After securing planning permission last year, Pure announced plans for the Brent Cross expansion earlier this year.

The company also has a 56MW facility in development in Park Royal alongside Segro.. Thank you for subscribing to our EMEA newsletter series.. More in Construction & Site Selection.