G42 signs MoU for AI infrastructure in Greece DCD Studio: Equipping an AI future with Adrian Guggisberg, ABB Cooler Master announces 2.5MW in-row CDU Generative Bionics plans AI data center and humanoid robotics factory in Italy Data Centers Bring Boom Times, But Will Gains Last? AWS plans to expand data center footprint in Montgomery County, Missouri DCD Studio: AI’s power problem with Varun Sivaram, Emerald AI Bull awarded €40m to deliver HLRE-5 supercomputer to the German Climate Computing Center Kao Data to host CommonAI’s AI Scaling Inference Lab at Harlow data center Fewer Care Delays, More Cost Savings: Nationwide Diagnostic Image Exchange Is Possible With TEFCA Ukraine’s Atesh attacks comms tower in Russia’s Belgorod region Reserve Bank of India launches data center in Bhubaneswar, Odisha Suki Secures $90 Million | Confido Health Expands Agentic Operating Platform ZutaCore details new two-phase boiling technology for liquid-cooled data centers AWS capacity “largely” sold out in 2027, Amazon CEO claims

ERCOT to complete Texas data center audit by December

The Electric Reliability Council of Texas (ERCOT) has said it intends to complete Governor Greg Abbott’s audit of all data centers seeking a grid connection by December.. 04 Aug 2026. Abbott directed ERCOT and the Public Utility Commission of Texas (PUCT) to undertake a comprehensive audit of all data center projects currently advancing through ERCOT’s interconnection process early last month..

As part of the audit, the PUCT and ERCOT were instructed to gather information detailing the extent to which data centers are paying their own way, the extent to which they are providing their own power or relying on the grid, the extent to which they are bringing their own water supplies and/or reusing water rather than relying on local communities, whether they are using measures to reduce impacts on neighboring property owners and communities, and finally information detailing the ownership and controlling interests in the project.. The grid operator said that it intends to complete the audit of the approximately 300 planned data centers seeking a grid connection by December 10, 2026.

It added that it will be a necessary step for its Batch Zero study process to continue and for grid interconnections of the large loads to resume.. According to Chad Seely, the grid operator’s senior vice president of regulatory policy, general counsel, and chief compliance officer at ERCOT, the process will include a comprehensive report on the verification and audit process delivered to the PUCT a week before its open meeting that month..

“We expect to start sending those out as early as the end of the month, and into the first part of September, and then as we move forward into October and November, there may be additional rounds of RFIs,” Seely said.. Texas is fast becoming a new hotspot for data center development.

At present, ERCOT is considering more than 474GW of connection requests, which is more than five times the state’s record peak electricity demand. Of that capacity, approximately 90 percent is attributed to data center load.. Due to the audit, reports suggest that up to 20 percent of the US’ entire data center pipeline could be delayed.

The financial impact of Governor Abbott’s audit, which would impact almost 49.8GW of projects seeking a grid connection, could be upwards of $8 billion by the first quarter of 2027. Should the pause extend further, the risk would become more extreme.. More in Grid Level.

27 Mar 2026. More in North America. 26 Aug 2026.

20 May 2026

 